The contractor, D’Ambra Construction, has installed new water main in Metacom Avenue from Robin Drive to Carr Lane.

In anticipation of increased July 4th traffic in Bristol, no work will take place from June 27 through July 4. All trenches will be paved, trucks and equipment will be stored away from Metacom Avenue and the project area will be cleaned. There may be workers onsite testing the newly installed mains. Normal operations will resume on July 5th.

We anticipate the remaining new water main to be installed in Metacom Avenue will be complete by the end of July. Additional connections, pipeline testing, and work on side streets will continue through August.

new-mains-installed-metacom
New water main and valves being prepared for installation

We apologize for the inconvenience to residents and motorists during this improvement project. If you have any questions, feel free to contact us at 245-2022. For emergencies during non-office hours, call 245-5071.