Contractor:                W. Walsh Company, Inc.

Project Budget:         $2,500,000

Project Overview:

BCWA awarded the 2023 water main rehabilitation project to W. Walsh Company.  The project budget is $2,500,000, including construction, traffic control, road restoration, inspection, and other costs.   Work included the cleaning and cement-mortar lining of 9,400 feet of cast iron water mains and the installation of 1,950 feet of new ductile iron water mains and 450 feet of new polyethylene water mains.  These improvements will help improve the reliability, flow, and water quality throughout our system.

 